The Cost of Waiting: How Delay Quietly Destroys Margin

  • Writer: RESTRAT Labs
    RESTRAT Labs
  • 5 hours ago
  • 17 min read

When work slows down, your margins shrink. Delays - whether from waiting on approvals, stalled handoffs, or missing inputs - quietly pile up costs. These hidden costs don’t show up in reports but directly eat into profits. The longer tasks sit idle, the more coordination, rework, and overhead expenses grow. Revenue is delayed, errors multiply, and margins erode.

Here’s the key takeaway: Every delay has a financial cost. For example, a sports manufacturer lost €300,000 annually due to slow invoice processing, while Maersk Line saw an $8 million revenue loss from a 38-week delay. Yet, 85% of managers don’t know their specific Cost of Delay (CoD).

To protect your margins:

  • Measure delays in dollars per time unit (Cost of Delay).

  • Prioritize work logically, not by gut instinct.

  • Limit work in progress (WIP) to avoid bottlenecks.

  • Streamline approvals and clarify decision rights.

Delays are more than just a scheduling issue - they’re a direct hit to profitability. Fixing them starts with better systems and faster workflows.

The Hidden Cost of Delays: Key Statistics on How Waiting Destroys Business Margins

Cost of Delay: Theory & Practice with Donald Reinertsen


Defining the Cost of Waiting

The cost of waiting refers to the financial penalty that increases the longer tasks or projects remain incomplete. Don Reinertsen, in his book The Principles of Product Development Flow, defines Cost of Delay (CoD) as "the impact of time on the outcomes an organization hopes to achieve." Put simply, it’s the dollar value lost for every time unit work is delayed. This concept highlights how every moment of delay can directly chip away at an organization’s profit margins.

Organizations tend to fall into two categories. The first group views delays as an inevitable part of operations, often hidden in queues and addressed through gut-based prioritization. These teams aim for nearly 100% resource utilization, believing it maximizes efficiency. The second group, however, measures delay as an economic factor. By calculating the cost of waiting and making queues visible, they prioritize work based on logic and financial impact rather than intuition [1].

"Cost of Delay is the golden key that unlocks many doors. It has an astonishing power to transform the mindset of a development organisation."Donald G. Reinertsen

Quantifying delay provides a huge advantage. For instance, if a team knows that delaying a feature costs $200,000 per week, decisions like expediting work or hiring additional help become straightforward. Yet, around 85% of product managers - and a similar percentage in other fields - are unaware of their specific Cost of Delay [2]. This lack of knowledge often leaves organizations guessing, unable to differentiate between tasks that safeguard profits and those that diminish them.

The longer the wait, the steeper the cost. As systems near full capacity, delays don’t just grow - they multiply. For example, a system running at 95% capacity faces exponentially longer delays than one at 90%. Extended feedback loops mean errors go unnoticed for longer, while coordination costs can eventually outweigh the value of the work itself [6]. Organizations that treat delay as an unavoidable overhead often underperform compared to those that prioritize speed and manage delay as a measurable factor.


Don Reinertsen's Cost of Delay Framework

Reinertsen’s framework connects value and urgency by calculating delay in terms of dollars per time unit [3]. This shifts prioritization from subjective judgment to economic reasoning. One key tool in this process is CD3 (Cost of Delay Divided by Duration), which ranks tasks based on value delivered per unit of time. By sequencing work this way, teams can maximize the value they deliver with their limited capacity.

Studies show that even within the same team, intuitive estimates of Cost of Delay can vary by as much as 50 to 1. This highlights the risks of relying purely on gut instinct. By using standardized financial assumptions, organizations can visualize the true cost of waiting and avoid system distortions. For example, Maersk Line applied this framework to a feature that had been stuck in queues for 38 weeks. With a Cost of Delay of over $200,000 per week, the delay amounted to nearly $8 million in lost revenue [3]. Once they began using CoD metrics, Maersk significantly improved their workflows - not by working faster, but by spotting and eliminating unnecessary waiting.

From here, we move to operational bottlenecks, examining Eliyahu Goldratt’s insights on system constraints.


Constraints and Throughput: Eliyahu Goldratt's The Goal

In The Goal, Eliyahu Goldratt explains how delays worsen by focusing on system constraints and throughput. His key insight? Every system has a bottleneck - a single point that limits overall output. Any time lost at this bottleneck directly reduces profits. Goldratt’s approach shifts the focus from keeping everyone busy to ensuring work flows efficiently. Traditional methods often aim for maximum resource utilization, but this can lead to long queues, slower feedback, and increased cycle times. Instead, prioritizing throughput - the rate at which value is delivered - can prevent these issues.

The practical takeaway is simple: find the constraint, ensure it’s never idle, and align all other processes to its pace. For instance, in trades, the constraint might be a licensed electrician or a key piece of equipment. In hospitality, it could be a decision-maker or a limited vendor. Wherever the bottleneck lies, delays at this critical point are far more costly than elsewhere. Moreover, focusing on isolated improvements - like speeding up approvals - can backfire, creating imbalances that worsen delays overall.

Next, we’ll explore how Little’s Law ties work in progress, throughput, and cycle time to the cost of waiting.


Little's Law: Connecting WIP, Throughput, and Cycle Time

Little’s Law provides a simple yet powerful formula to understand how work and delays are connected:

Cycle Time = Work in Progress (WIP) ÷ Throughput

This means that to shorten cycle times - and reduce the cost of waiting - organizations have two options: lower WIP or increase throughput. While many teams try to boost throughput by working harder, Little’s Law suggests that cutting down WIP is often the smarter move.

Excessive WIP causes queues to grow, leading to coordination challenges, frequent context switching, and delayed feedback - all of which drive up costs. When capacity utilization approaches 100%, even small demand fluctuations can cause cycle times to skyrocket [6]. The solution? Build slack into the system. Allowing for idle time absorbs variability and keeps workflows smooth [7]. In practice, this means controlling the number of active tasks rather than pushing for constant busyness. Whether it’s limiting open jobs in a trades business or capping projects in hospitality, managing WIP is key to reducing delays and maintaining efficiency.

With this foundation, we can now explore where delays tend to hide and how they erode profits.


Where Waiting Hides in Workflows


Common Wait States

Delays in workflows often go unnoticed. Unlike manufacturing, where bottlenecks are easy to spot as inventory piles up, the queues in knowledge work - like documents, decisions, and approvals - are invisible. This lack of visibility makes waiting especially harmful because, by the time anyone realizes there's an issue, the damage to margins has already been done [6].

The most frequent causes of delays are tied to handoffs, approvals, and dependencies. For example, an invoice might pass from operations to accounting to management, sitting idle in each inbox for days. A job may grind to a halt while waiting for a permit that needs multiple signatures. Or a project could be derailed because a vendor quote expired while awaiting approval. Even small pauses can snowball into major disruptions since most of the total cycle time in workflows is spent waiting, not working [3][4].

Here’s a real-world example: in the trades, a commercial HVAC retrofit might wait four days for a building manager to approve access to mechanical rooms. During this downtime, the crew moves on to another job, only to return later - requiring a second mobilization that adds $1,200 in labor and equipment costs. The actual work only takes six hours, but the waiting ends up costing far more than the task itself.

Another hidden source of delay is decision queues. When prioritization is based on gut instinct or the preferences of the most senior person in the room - rather than on economic urgency - important projects get stuck while less critical tasks consume resources [3][5]. Without clear metrics, the cost of these delays remains hidden, and businesses continue making decisions that quietly eat away at their margins. Waiting isn’t just a neutral pause; it compounds over time, eroding both efficiency and profitability.


The Economic Impact of Hidden Waiting

The financial consequences of hidden waiting can be staggering. Large queues demand constant updates, coordination meetings, and tracking efforts - sometimes costing more than the original work itself [6]. When feedback loops stretch from a few days to weeks or even months, small errors can snowball into massive rework. For instance, at Maersk Line, a single feature spent 38 weeks stuck in various queues. With a Cost of Delay exceeding $200,000 per week, this delay resulted in nearly $8 million in lost revenue - not because the work was flawed, but because the system prioritized approver convenience over speed [3][4].

Waiting also creates mismatches between teams. Upstream workers might sit idle while downstream bottlenecks are overwhelmed. This fragmented capacity leads to rushed decisions and higher costs [6]. In freight brokerage, for example, a seven-day delay in collecting proof-of-delivery documents can cut 5% from gross margins due to interest costs on tied-up working capital [9]. In solar installations, delays in approvals can trigger contract cancellations, which account for up to 25% of pre-installation soft costs. Median cancellation rates hover around 33% [8]. Similarly, inefficiencies in procurement processes can drive up transaction costs by 15–20% [10].

The trend is clear: waiting increases overhead, disrupts cash flow, and leads to quality issues. The longer work sits idle, the more context gets lost, and the more costly handoffs and errors become, steadily chipping away at margins.


How Delay Erodes Margins

Delays don't just stretch timelines - they quietly chip away at margins by driving up indirect costs, compromising quality, and cutting into revenue potential.


Indirect Costs and Coordination Overhead

Delays create ripple effects that go far beyond the surface. When a project stalls, teams often end up spending more time and effort just to keep things on track. This means extra meetings, more emails, and constant stakeholder updates - all of which pile on coordination costs. For instance, project managers can spend up to 90% of their time on communication alone[12]. Yet, traditional accounting systems rarely factor in these hidden expenses.

In supply chains, delays lead to products sitting in warehouses longer, racking up storage fees[11]. In service industries, delays tie up team members who could otherwise be working on revenue-generating projects, creating opportunity costs that don’t show up on financial statements[12]. To make matters worse, teams often resort to overtime or hiring contractors to catch up, further inflating costs[12]. These indirect costs can snowball quickly, making delays far more expensive than they initially seem.


Expediting, Rework, and Quality Slips

When teams scramble to recover lost time, the costs don’t stop at overtime. Organizations often turn to expensive measures like air freight, which can be 5 to 10 times pricier than ground or sea shipping[14]. Similarly, sourcing components from brokers during shortages can come with markups of 10% to 30%, while contract manufacturers may charge 10% to 25% more to prioritize delayed production[14].

This rush to meet deadlines often leads to cutting corners, especially in testing and quality checks. The result? Defects and errors that require costly rework and cause further delays[12]. Manual processes, like data entry between disconnected systems, can introduce mistakes that compound the problem[15]. For example, AstraZeneca managed to slash global invoice approval times from 60 days to just 4.5 days by eliminating manual bottlenecks, boosting productivity by 93% and avoiding downstream quality issues[13]. Without careful planning, the scramble to recover from delays can lead to a vicious cycle of escalating costs and compromised quality.


Revenue Timing and Customer Satisfaction Risks

Delays don’t just inflate costs - they can also shrink the window for earning revenue. For products tied to fixed timelines, like those with expiration dates or seasonal demand, a delayed launch can significantly reduce sales potential[16]. Missing a key launch date in a seasonal market often means starting over to regain lost momentum[17][18]. This phenomenon, known as "Peak Reduction Cost", happens when delays not only defer revenue but also dampen peak sales as early adopters turn to competitors[20].

"If you only quantify one thing, quantify the cost of delay." – Don Reinertsen, Author of The Principles of Product Development Flow [16]

Customer dissatisfaction can amplify these risks. For instance, delays in hiring can overload existing staff, leading to missed deadlines and a dip in service quality[18]. Meanwhile, outdated or delayed data costs businesses money - 85% of data leaders acknowledge this issue. Globally, inefficient inventory management tied to delayed information results in a staggering $1.1 trillion in losses annually[19]. The longer work sits idle, the more cash is tied up, slowing down cash flow and straining working capital. These combined effects make the true cost of delays impossible to ignore.


Example: The Hidden Cost of a 5-Day Delay

Take a commercial electrical project delayed by five days while waiting for a building owner to approve changes. During this time, the project manager follows up twice, the estimator adjusts the quote once, the scheduler reassigns crews twice, and the foreman coordinates with a subcontractor. That’s six separate coordination efforts, none of which can be billed to the client. If each task takes 30 minutes at $75 per hour, the hidden labor cost adds up to $225. Add $800 in remobilization expenses, and this seemingly minor delay ends up costing over $1,000 in lost margin - doubling the actual cost of just six hours of work.


Delay Economics in Small Business Operations

The dynamics of delay affect businesses of all sizes. Whether you're running a $5 million contracting firm or a $500 million enterprise, the core economic principles remain the same. For small businesses, delays often show up as "margin leaks" and operational headaches. The culprits? Coordination costs, idle capacity, rushed fixes, and missed opportunities - factors that are universal, even if the scale differs.


Trades and Services: The Cost of Waiting on Parts and Approvals

For small businesses, delays can chip away at margins just as they do for large enterprises. The difference is that, in smaller operations, these margin leaks are felt more acutely.

Take the example of a commercial HVAC contractor. They schedule a crew to install ductwork, but the job is held up because a permit approval sits on a city planner's desk for eight days. While waiting, the crew gets reassigned, the customer repeatedly calls for updates, and the project manager spends hours juggling subcontractor schedules. Once the permit is approved, remobilizing the crew adds about $1,200 to the project's costs. The result? The job's margin drops from 18% to 11%. In this case, the waiting costs more than the labor itself.

Parts delays can be just as disruptive. Imagine an electrical contractor waiting five days for a specialty breaker panel. The electrician moves to another job site, only to find that work there isn't ready either. This shuffle causes billable hours to drop by 30% for the week. On top of that, the frustrated customer negotiates a $600 concession, even though the delayed part only cost $400. When all is said and done, the contractor loses an estimated $2,100 in labor and margin. In service-driven businesses, these kinds of delays translate directly into lost revenue.


Hospitality: Revenue Loss from Delays That Snowball

In the hospitality sector, delays can cascade into significant revenue losses. Picture a boutique hotel with a plumbing issue in one of its premium suites. Fixing the problem requires a vendor's input on replacing a fixture, but the vendor takes four days to respond. Meanwhile, the hotel's maintenance team starts another project, only to pause it once the vendor finally replies. What should have been a three-day repair stretches into nine days. At $320 per night, the suite loses nearly $2,000 in revenue for the extra six nights it’s offline. Add the $850 repair cost, and the delay's financial impact far outweighs the repair itself.

A similar pattern occurs at larger scales. For example, in 2014, Maersk Line identified a project feature that spent 38 weeks stuck in various queues. The delay cost them over $200,000 per week, totaling nearly $8 million in lost revenue [4][3]. While small businesses deal with smaller figures, the same cascading delays and margin leaks happen when decision-making bottlenecks or processes stall.


Owner Bottlenecks: The Hidden Costs of Decision Queues

In owner-led businesses, delays often stem from decision-making bottlenecks. The owner becomes the sole gatekeeper, creating queues that slow everything down.

Consider a landscape contractor waiting three days for the owner to approve a material substitution. Or a design-build firm with multiple proposals sitting in the owner's inbox, each requiring sign-off before moving forward. A property management company might face similar delays, unable to schedule vendor work until the owner reviews bids. The issue isn’t that the owner is slow - they’re simply overwhelmed. But because the system relies on one person for decisions, it creates what Donald Reinertsen calls "invisible inventory" [6]. These bottlenecks amplify waiting costs and erode margins over time.

When every decision requires the owner’s input, the delays pile up. This not only drains motivation but also chips away at profitability. The problem isn’t individual inefficiency - it’s a system designed for control rather than smooth, reliable workflows.


Designing Flow to Reduce Waiting

Reducing delays often requires rethinking how work flows through a system. The aim is to create a process where tasks move smoothly without piling up or stalling at critical points. This involves reconsidering how work enters the system, how decisions are made, and how tasks transition between stages. Here’s a closer look at strategies to minimize waiting and protect margins.


Limiting Work in Progress (WIP)

One of the simplest ways to cut down on delays is to limit the number of tasks being worked on at the same time. When too many items are active, context switching increases, bottlenecks stay hidden, and cycle times stretch out. Setting WIP limits creates a pull system - new work only starts when there’s available capacity. This makes bottlenecks easier to spot and address [21][22].

"Stop starting, start finishing." – Planview [23]

For instance, a team might cap active tasks at team members plus one. A five-person team, for example, would set a WIP limit of six. The Aerosud IT team applied this principle and doubled their throughput from 60 to 120 tickets in just three days by finding their optimal WIP limit [24]. While it might feel counterintuitive, fewer active tasks often lead to faster completion because there’s less competition for attention.

For small business owners, this could mean limiting active bids, starting fewer projects simultaneously, or capping pending decisions. Although it might feel restrictive at first, this discipline creates the breathing room needed to finish tasks efficiently and reduces the coordination overhead that eats into margins.


Clarifying Decision Rights and Approval Paths

Clear decision-making paths are crucial for keeping work moving. Many delays happen when it’s unclear who has the authority to approve changes, substitutions, or purchases. Defining decision rights - who owns, reviews, and signs off on tasks - can eliminate this confusion [25]. Establishing criteria for what’s "ready for approval" also prevents wasted time on unnecessary back-and-forth.

Organizations with efficient decision-making processes often see substantial benefits, including 2.5 times higher growth and 30% higher returns on invested capital [27]. Streamlining approvals can also cut time to market by 40% and boost profitability by 25% [26]. For example, in 2019, a state government agency used a RACI framework to clarify decision roles, reducing its citizen appeal process from seven months to just one [27].

In smaller businesses, tiered approval systems can be especially effective. Routine, low-value decisions - like minor material substitutions - can be handled by project managers, leaving owners to focus on bigger decisions. Setting thresholds (e.g., "contracts over $50,000 need CFO approval") and designating a tiebreaker for disputes ensure decisions are made quickly and by the right people [25][26]. The goal isn’t to eliminate approvals but to make them fast, predictable, and proportional to the stakes.


Stabilizing Handoffs and Removing Queues

Handoffs between stages - like moving a job from estimating to scheduling or from the field to billing - are frequent bottlenecks. To keep these transitions smooth, it’s important to establish clear protocols so the next stage is ready to take over.

One effective method is paced order release, where work is added based on actual capacity (labor, equipment, space) rather than optimistic assumptions [28]. This prevents congestion and avoids disruptive priority shifts. As Hector Sunol, CEO of Cyzerg, explains:

"Order release should pace work based on the reality of your labor, equipment, staging space, and carrier cutoffs." [28]

Another approach is phase-gate validation, where milestones like design completion, permit approval, or material delivery are formally signed off before moving forward. This locks in progress and prevents late changes from derailing the schedule. Architecture and engineering firms that adopted integrated project tracking saw a 21% revenue boost and a 44% drop in over-budget work within a year [30]. For service businesses, requiring all "quick changes" to go through a formal cost and schedule review can help prevent unbilled scope creep. Reducing travel and context switching - whether by shortening physical distances or using rituals to refocus - can also improve flow [28][29].

The key is to match work release rates with completion rates, ensuring every handoff includes clear criteria for what "done" means. This approach reduces hidden coordination costs that often eat into profits.


Measuring Wait States

You can’t fix what you don’t measure. While many businesses track overall cycle time, they often overlook the distinction between active work time and waiting. For example, a 12-day job might involve only 3 days of actual work, with the rest spent waiting on approvals, parts, or crew availability.

Start by identifying your top three sources of waiting - like permit delays, vendor responses, or owner approvals - and measure their frequency and duration. This makes the hidden costs of delays more tangible.

When calculating the impact on margins, use broad ranges instead of overly precise numbers. For instance, "Jobs delayed over 5 days due to permit approval typically add $1,000–$1,500 in coordination and remobilization costs, reducing margin by 5 to 8 percentage points." This approach keeps the focus on actionable insights rather than false precision. The goal isn’t to eliminate all waiting - some delays are inevitable - but to make them visible and manageable, allowing for targeted improvements where they matter most.


Conclusion: Execution Reliability Protects Margin

Execution reliability isn't just a nice-to-have; it's a critical shield for protecting margins. As we've seen, delays don’t just slow things down - they snowball into coordination headaches, rework, rushed fixes, and missed opportunities. These hidden costs chip away at margins long before the financial impact becomes obvious. The organizations that consistently protect their margins aren’t the ones squeezing more out of their teams or relying on last-minute heroics. Instead, they build flow into their systems from the very beginning.

W. Edwards Deming captured this perfectly: "A bad system will beat a good person every time." [1] Reliable execution stems from thoughtful system design - streamlined handoffs, clear decision-making processes, manageable workloads, and transparency around delays. These aren’t issues of individual effort; they’re the result of deliberate choices in how work is structured. Earlier examples, like the sports article manufacturer and AstraZeneca, highlight that protecting margins is about system discipline, not individual push.

The numbers back this up: organizations that balance long-term system design with short-term execution achieve 47% higher revenue growth and 36% higher profitability compared to those that focus narrowly on one or the other [31]. In a world where labor remains tight and uncertainty is the norm, reducing waiting times becomes a real competitive edge. It safeguards both margins and capacity - without the need to increase headcount.

By quantifying the cost of delay, businesses can shift from gut-feel decisions to ones grounded in economic logic. It turns what’s often invisible into something measurable - and, most importantly, fixable.

Protecting margin starts with designing systems that ensure reliable flow - not relying on extraordinary effort. Whether it’s clear handoffs, controlled workloads, or fast feedback loops, execution reliability is the product of intentional design. Organizations that maintain this discipline not only safeguard their margins but also position themselves to thrive - whether they’re multinational corporations or small businesses. Hidden margin leaks don’t stand a chance against a well-designed system.


FAQs


How do I calculate our Cost of Delay in dollars per day?

To figure out your Cost of Delay in dollars per day, start by estimating how much economic value is lost for every day a project or task is delayed. Take the total expected value or revenue impact of the work and divide it by the time period it impacts. Tools like spreadsheets can help you map out how delays chip away at value over time. By focusing on the daily financial impact, you'll get a clearer picture of the cost of waiting.


Where does waiting hide in my workflow if everyone looks busy?

Waiting tends to lurk in places like handoffs, approvals, vendor dependencies, scheduling issues, permit gates, and missing inputs. These delays don’t always look like obvious downtime but often pile up as queues, dragging down the overall workflow. For instance, tasks stalled while waiting for parts or inspections can subtly chip away at profit margins by stretching cycle times and increasing indirect costs - even when it seems like everyone is actively working. Pinpointing and tracking these bottlenecks is essential to keep things moving efficiently.


What’s the fastest way to reduce delays without adding headcount?

The fastest way to cut down on delays without adding more staff is to revamp the system itself. Start by ensuring decision rights are crystal clear, cutting out unnecessary approval steps, streamlining handoffs, and keeping work-in-progress manageable. These adjustments help processes move more smoothly and speed up decision-making, stopping delays from quietly eating away at profits.


Related Blog Posts

 
 

© 2017-2026 Restrat Consulting LLC. All rights reserved.  |  122 S Rainbow Ranch Rd, Suite 100, Wimberley, TX 78676  Tel: 512.730.1245  |          United States

Proudly serving the Austin Metro area              TEXAS

Texas State Shape

Subscribe for practical insights and updates from RESTRAT

Thanks for subscribing!

Follow Us

bottom of page